Method 1: The territorial officer, as the owner, must be the first to perform the LTCT. Other lockers should remove their locks and tags when they have finished their work. Only after the owner is satisfied that the work is complete and the machine is safe to operate can the owner remove their own locks and tags. The owner is the last to remove the lock and tag.
Mode 2: Localised personnel perform Lockout and tagout(Lockout and tagout by the electrician on duty in the distribution room), operators witness the locking process and preservation, and test run to confirm the successful energy isolation before operation. After the work is completed, it should be handed over to the territorial personnel (electrician on duty) and informed of the condition of the equipment.